§As a whole, MDT is a “+2”
project, but should probably be “+3” or “+4” based on its
dependencies
§
§M3 met on November
16
§
§M4 slipped from January
4 to January 22
§
§M5 met on February
23
§
§M6 slipped from April 6
to April 10
§
§M7 slipped from May 18
to May 24